BUILDING PROJECT UPDATE

 

Abram Lansing School

Summary of work Date of completion/anticipated completion
New sidewalk and drop-off lane Aug. 2007
UPK center addition with four new classrooms June 2010
Additional parking areas to add more teacher/parent parking Sept. 2010
Relocate playground Sept. 2010
Renovation of offices and meeting areas throughout building Sept. 2010
Upgrade/renovate four bathrooms Sept. 2010
Mechanical/electrical upgrades throughout Sept. 2010
Maintenance upgrades throughout Sept. 2010
Gym/stage upgrades Oct. 2010

 

Harmony Hill School

Summary of work Date of completion/anticipated completion
New roof Aug. 2007
New windows, shades and screens Sept. 2007
Replacement of ceiling tiles from water damage Sept. 2007
Site work improvements including but not limited to repaving parking lots, Madelon Hickey Way and replacing sidewalks up to school Sept. 2010
Renovation of offices and meeting areas throughout Sept. 2010
Maintenance upgrades throughout Sept. 2010
Mechanical/electrical upgrades throughout Sept. 2010
Two-story classroom addition Nov. 2010

 

Van Schaick Grade School

Summary of work Date of completion/anticipated completion
Construction of 1,600 square-foot addition Sept. 2009
Construction of new access road from Van Schaick Avenue Sept. 2009
Mechanical/electrical upgrades throughout Sept. 2009
New water heater Sept. 2009
Purchase of corner lot on Continental and Myrtle avenues Summer 2008
Gymnasium upgrades Sept. 2009
Renovation of offices and meeting areas throughout Sept. 2009
RRenovations and upgrades to the entire existing building, including full classroom and bathroom renovations and window replacements Sept. 2009
Radon mitigation system/td> Sept. 2009
Modified soccer field Fall 2010
New parking lot and street design Sept. 2010
Additional site improvements and park upgrades Sept. 2010


Cohoes Middle School

Summary of work Date of completion/anticipated completion
New roof Aug. 2007
New boiler Sept. 2007
New one-story addition off gym for multipurpose use May 2010
Site work improvements including remediation of existing retaining wall, new sidewalk and curb along Columbia Street as well as front entrance upgrades Sept. 2010
Maintenance upgrades throughout Sept. 2010
Mechanical/electrical upgrades throughout Sept. 2010


Page Avenue School

Summary of work Date of completion/anticipated completion
New roof Aug. 2007
New boiler Sept. 2007
Heating system replacement Sept. 2007
Radon mitigation system July 2008
Site work improvements including a new chain link fence, sidewalks and an updated parking area  Aug. 2008
Masonry maintenance updates Nov. 2008

 

Cohoes High School

Summary of work Date of completion/anticipated completion
New roof Aug. 2007
New boilers Sept. 2007
Water heater replacement Aug. 2008
Improvements to drainage in boiler room to protect the area from future water damage Sept. 2008
Music/chorus room upgrades Sept. 2010
Maintenance upgrades throughout Sept. 2010
Mechanical/electrical upgrades throughout Sept. 2010
Cafeteria/kitchen upgrades Sept. 2010
Auditorium upgrades Dec. 2010
Construction of new gym and suspended track May 2011
Renovation of office and meeting areas throughout May 2011
New entrance lobby to new gym and auditorium May 2011
Construction of new project-based learning classrooms May 2011
New guidance suite May 2011